South Korea's push to become a global artificial intelligence hub moved from policy documents to construction equipment on November 28, 2026, when GS Group staged a groundbreaking ceremony for a 1.2-gigawatt AI data center in the eastern coastal city of Donghae. The site is the Bukpyeong No. 2 General Industrial Complex in Gangwon Province, and the event marks the first construction start among the gigawatt-class facilities bundled into the government's Three Mega-Projects for Korea's Great Leap Forward, a package announced in June.
GS Group is not stopping at 1.2 gigawatts. The conglomerate plans a 2.4-gigawatt campus delivered in two phases of 1.2 gigawatts each, a buildout its leadership describes as the starting point for the country's rise as a global AI hub. The first phase carries a 15 trillion won investment plan, while the full two-phase construction is estimated at about 30 trillion won before processors and memory are added to the bill.
President Lee Jae Myung attended the ceremony and framed the day in stark terms. Yonhap News Agency reported on November 28 that Lee called the global AI technology race a silent war at the national level, and warned that a single step behind would leave a country a permanent follower while a step ahead could make it a leader that changes the game. He pledged that the government would mobilize all its capabilities to ensure South Korea firmly establishes itself as a leading country that sets global standards and charts the way forward.
The Donghae ceremony is one node in a considerably larger national program. The government aims to build 8.4 gigawatts of AI data center capacity in a first phase together with SK, GS and Naver, and the three companies are expected to invest about 550 trillion won, Aju Press reported on November 28. The Ministry of Science and ICT said Donghae is the first gigawatt-class AI data center to break ground among the three mega-projects.
Key Facts
The ceremony drew roughly 270 people, according to Aju Press. Alongside the president were GS Group Chairman Huh Tae-soo, Science and ICT Minister Bae Kyung-hoon, GS Holdings Vice Chairman Hong Soon-ki, GS E&C CEO Huh Yoon-hong, GS AI Infra CEO Do Hyun-soo and GS E&R CEO Hwang Byung-so. Chairman Huh told the gathering that GS intends to build a world-class AI data center at the site and to make it the starting point for Korea to emerge as a global hub in the AI era.
The money attached to the project is large and, depending on what is counted, wide ranging. The Seoul Economic Daily reported on November 28 that GS will invest 15 trillion won, or $10.2 billion, in the 1.2-gigawatt first phase, while The Herald Business put that same 15 trillion won figure at $11.2 billion. For the complete 2.4-gigawatt campus, Aju Press reported a cost of about 30 trillion won ($22.4 billion), rising to as much as 120 trillion won once graphics processing units and memory chips are included. Yonhap News Agency placed the upper bound at 120 trillion won, or $89.79 billion.
The first phase occupies about 264,000 square meters, or roughly 80,000 pyeong, of the Bukpyeong No. 2 industrial complex. GS will divide the land into three zones to build a combined 700 megawatts of capacity, then add a separate 500-megawatt center on an adjacent site. A 100-megawatt first zone is targeted for completion in the second quarter of 2028, with a 200-megawatt second zone and a 400-megawatt third zone following later that year, and the 500-megawatt facility coming online during 2029.
Employment projections are equally sizeable. GS estimates the build will require about 70,000 cumulative workers during construction and about 1,000 direct and indirect workers once the campus is operating, figures carried by both the Seoul Economic Daily and The Herald Business. The company has presented the project as one that will create more than 70,000 jobs and boost the local economy through phased completions running through 2029.
GS said it selected Donghae for the region's abundant power generation capacity and the possibility of using seawater for cooling, Aju Press reported on November 28. Gangwon Province and Donghae completed key permits within three months, a speed the president publicly praised at the ceremony. GS established GS AI Infra in June, completed a power grid impact assessment and construction approval, and signed memorandums of understanding with LS Electric, POSCO, LG Uplus and Honeywell Technologies.
Analysis
What this really means is that South Korea has chosen to compete on infrastructure rather than only on models or applications. A 2.4-gigawatt campus is not a corporate pilot project; it is a piece of national industrial policy poured in concrete, and the government is treating electricity, land and permits as strategic assets in an AI race it describes as a silent war.
The structure of the spending reveals where the real constraint sits. Fifteen trillion won buys 1.2 gigawatts of buildings and power equipment, and roughly 30 trillion won buys twice that, but the ceiling of 120 trillion won appears only when graphics processing units and memory chips enter the ledger. That gap means the overwhelming majority of the eventual cost is silicon, not civil engineering, so the project is as much a procurement strategy for chips as it is a construction program. GS brings construction, energy and retail affiliates rather than hyperscale cloud experience, which makes the state's backing and the speed of permitting central to whether the schedule holds.
The published dollar conversions do not agree: the same 15 trillion won is described as $10.2 billion by the Seoul Economic Daily and $11.2 billion by The Herald Business, and 30 trillion won is given as $22.4 billion by Aju Press. Those differences suggest the economics are still being framed rather than fixed, even as the won denominated figures of 15 trillion and 30 trillion stay consistent across coverage.
The regulatory timetable is telling as well. The Ministry of Science and ICT issued a draft enforcement decree on November 20 for a special act on promoting the AI data center industry, effective March 2027, which would exempt AI data centers outside the Seoul metropolitan area of up to 50 megawatts from power grid impact assessments and create a one-stop permit process, with a public hearing set for December 9. The bigger picture here is that construction is already underway before the legal framework that supports it is final, a sign of how far political urgency has outrun the ordinary rulemaking sequence.
Why It Matters
For Gangwon Province, this is the first megaproject in the region, and Cheong Wa Dae said it will serve as a key driver of new growth and vitality for the regional economy. Yonhap News Agency noted that once completed the facility is expected to become one of Asia's largest AI infrastructure complexes, a claim that puts a fishing and manufacturing city on the same map as the continent's biggest computing campuses.
The project also tests whether the country's 8.4-gigawatt first phase target is realistic. Donghae accounts for 1.2 of those gigawatts on its own, and the government has tied the remainder to SK and Naver. If the Donghae build stays on schedule through 2029, it becomes the template for the other two projects and for the special act's promise of faster permits outside the crowded Seoul metropolitan area.
On the ground, the effects are measurable in labor and supply chains. About 70,000 cumulative construction workers and roughly 1,000 permanent operational staff represent a durable local payroll that a coastal city of this size rarely sees, and the memorandums with LS Electric, POSCO, LG Uplus and Honeywell Technologies spread the benefit across Korean equipment, materials and telecom suppliers. The president reinforced the industrial framing after the ceremony by touring data center technologies from LS Electric and LG Electronics.
Next Up
The near term calendar is dominated by the first 100-megawatt zone, targeted for the second quarter of 2028, followed by the 200-megawatt and 400-megawatt zones later that year and the 500-megawatt center during 2029, when the full 1.2-gigawatt first phase is due to operate. The December 9 public hearing on the draft enforcement decree will show how quickly the one-stop permit regime and the 50-megawatt assessment exemption outside Seoul actually take shape.
Beyond Donghae, attention shifts to whether SK and Naver move their own gigawatt-class projects to construction, and whether the 550 trillion won pledged across the three companies materializes on the government's timetable. Lee closed his day in Gangneung at a seafood market, but the signal from Donghae was unmistakable: the country's AI strategy now has a construction schedule attached to it.